Decide Fast & Get 50% Flat Discount on This Special Offer | Limited Time Offer - Ends In COUPON CODE: SAVE50

PK0-005 Exam Dumps

PK0-005 Exam Dumps

CompTIA Project+ Certification Exam

Vendor: CompTIA

Exam Name: CompTIA Project+ Certification Exam

Questions with Answers: 138

Last Updated: 16-Jul-2024

PDF Exam Dumps

$29.50 $59

Download Demo
WEB Practice Test

$39.50 $79

Try Demo
PDF + Practice Test
$49.50 $99
money back guarantee logo

100% MoneyBack Guarantee

security and privacy logo

Security and Privacy

customer support logo

24/7 Customer Service

Free 3 Months Updates

CertsAway offers you 3 months updates on each exam purchase. Once you will buy any of our exam products you will be subscribed to free 3 months updates

24/7 Customer Support

We offer you 24/7 free customer support to make your learning smooth and hassle free. If you have any query regarding the material so feel to write us.

100% Money Back Guarantee

Your money is safe with CertsAway. We provide 100% money back guarantee to our respective customers. CertsAway makes your venture safe with its 100% refund policy.

Try Free Demo

We insist you to try our free demo before exam purchase. This demo will make you acquainted with the real exam product. 100% passing guarantee with CertsAway.com

CompTIA PK0-005 Exam Questions

CompTIA Project+ Certification Exam exams.

Question
During a gate review meeting, the deliverable was rejected by the customer. INSTRUCTIONS Review the dashboard. • Part 1: Drag and drop each task, placing them in the correct order based on the project change control process. • Part 2: Select the proper document(s) to be updated. If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Part 1:



Part 2:



 Answer: See the Explanation for the solution. Explanation: Part 1: Change Control Process: Consult the RACI matrix. Define new requirements and record changes. Assess the schedule, risk, and cost. Perform a demonstration. Obtain a sign off. Update and test the deliverable. Make an announcement on the company portal. The change control process is a sequence of steps that helps to manage and document any changes or modifications to a project scope, schedule, cost, quality, or resources. The change control process typically involves the following steps: Consult the RACI matrix. A RACI matrix is a tool that defines and clarifies the roles and responsibilities of each team member for each task or activity in a project. RACI stands for responsible, accountable, consulted, and informed. Consulting the RACI matrix can help to identify who needs to be involved or informed about the change request and how to communicate with them. Define new requirements and record changes. The new requirements and changes are the details of what needs to be modified or added to the project deliverables or objectives based on the customer feedback or request. Defining and recording the new requirements and changes can help to communicate and justify the need and rationale for the change and its implications on the project scope and quality. Assess the schedule, risk, and cost. The schedule, risk, and cost are the aspects of the project that may be affected by the change request. Assessing the schedule, risk, and cost can help to determine the impact and feasibility of the change and identify any possible alternatives or corrective actions to minimize or avoid its negative effects. Perform a demonstration. A demonstration is a presentation or show of how the modified or updated deliverable works or meets the customer expectations or requirements. Performing a demonstration can help to validate and verify that the change request has been implemented correctly and effectively and to obtain feedback or approval from the customer or stakeholders. Obtain a sign off. A sign off is a formal acceptance and approval of the change request and its deliverables from the customer or stakeholders. Obtaining a sign off can help to confirm that the change request has been completed successfully and satisfactorily and to close the change control process. Update and test the deliverable. The deliverable is the product or service that is produced or provided by the project. Updating and testing the deliverable can help to ensure that it meets the quality standards and criteria and that it works as expected after implementing the change request. Make an announcement on the company portal. The company portal is a platform or channel that allows internal communication and collaboration among employees within an organization. Making an announcement on the company portal can help to inform and update other team members or departments about the change request and its outcomes and to share any lessons learned or best practices from the change control process. Part2: Risk register: A risk register is a document that identifies, analyzes, and records the potential risks or uncertainties that may affect a project. Updating the risk register can help to capture any new or modified risks that may arise from the change request and to plan and implement appropriate risk responses. Schedule: A schedule is a document that shows the planned start and end dates, durations, dependencies, and progress of each task or activity in a project. Updating the schedule can help to reflect any changes or adjustments to the project timeline or milestones that may result from the change request and to monitor and control the project performance and delivery. Statement of work: A statement of work (SOW) is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. Updating the SOW can help to document any changes or additions to the project scope or deliverables that may be requested or agreed upon by the customer or stakeholders and to ensure alignment and agreement on what needs to be done and how it will be done. Change log: A change log is a document that tracks and records any changes or modifications that are made to the project scope, schedule, cost, quality, or resources during a project. Updating the change log can help to document the change request, approval, implementation, and impact of each change and ensure traceability and transparency.
Choose the Choices:


Question
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).
Choose the Choices:


Question
Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
Choose the Choices:


Question
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
Choose the Choices:


Question
During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
Choose the Choices:


Our Achievement

pencile in hand white icon
3000+ VALID EXAMS
student white icon
78,000 Satisfied Customers
comment emoji white icon
96% SUCCESS RATE
open book white icon
99% UPDATED EXAM DUMPS

What Our Clients Say